Allermuir North American Facility
Senator Allermuir
ESA provided civil engineering and site design for new 91,000 sf headquarters and manufacturing facility on 22 acre greenfield site. Site design included accommodations for future facility Phase 2, 3 and 4 campus expansions. Project approvals for the site included Monclova Township, Lucas County Engineer, Lucas County Sanitary Engineer and the City of Toledo. Site design included:
- Truck routing and turn evaluation for onsite truck movements.
- Parking for current building requirements with expansion for future building needs.
- Sanitary sewer and water main with future building connections.
- Storm system utilizing surface drainage with a combination of swales and piping.
Aggressive schedule required the site design to be issued for site plan approval 12 weeks after the start of design.